Problem

Construction of a 6-story parking garage and adjacent to a module block wall on the footprint of an existing parking lot required a skilled excavation company – all of which was complicated by discovery of a live water main and electrical duct bank underneath.

Solution

  • Handheld GPS and careful site review to confirm location of a live water main and electrical dock prior to rerouting
  • Smart, GPS, software-enabled bulldozers and excavators ensured fast and accurate grading and site cuts
  • Careful coordination and timing among electrical, plumbing and construction contractors
  • Background check and security clearances for managing spoils transportation from landside to airside dump site

Impact

Streamlined communication and a unique contract model eliminated scope gap concerns for the general contractor and ensured successful navigation of unforeseen challenges and material change orders.

O'Hare Parking Garage Project
O'Hare Parking Garage Project

O'Hare Parking Garage Project

Image from Clayco

O'Hare Parking Garage Project

Image from Clayco

Contact us to learn more about excavating services